07/14/13: Signed application and paid deposit &
started mortgage application with NVR
07/29/13: Decided to Mortgage shop
08/01/13: Completed wiring appointment selection
08/04/13: Decided to finance with Navy Federal instead of NVR
08/04/13: Had to resign documents as
specified by attorney (using power of attorney for my husband)
08/17/13: Complete Rug Rite Appointment
08/22/13: Pre-construction meeting
09/03/13: Footings poured
09/06/13: Foundation Completed
09/18/13: Lumber delivered framing scheduled to begin next
week
09/ 29/13: Framing completed
10/04/13: Pre-drywall meeting
12/06/13: Final walk-through inspection scheduled
12/09/13: Closing Scheduled (December closing at my request)
I also selected the double oven option does this effect how the fridge opens?
ReplyDeleteHi Gabrielle, I ended up getting the French door refrigerator. It doesn't come in contact with my oven (at least not that I've noticed). Besides whenever I open the oven its to put something in or take something out so its never open for long. The problem I do have is the wall next to the refrigerator. I can't open the right side wide. Overall I am very happy with my kitchen.
DeleteAlso, I didn't get the title backslash from Ryan and I'm glad I didn't! I was able to get the backslash of my choice installed for around $600 (materials and labor) through lowes. So please keep that in mind when you make your slections.